Saturday, January 29, 2011

New ceiling joists









New ceiling joists were installed over the master bedroom and the (old) lounge room in the old part of the house.
























A view of the new ceiling joists from the (old) lounge room.

Friday, January 28, 2011

Roof coming off








The eastern (back)
half of the roof over the old part of the house is coming off to make way for a new roof.






















The debris from the roof along the northern side of the house.

























The ceiling in the hallway has gone as well (looking to the west from the new extension).























Current status of the main bathroom.

Thursday, January 27, 2011

More carpentry







Another day of carpentry and brick laying. Two brick columns to support the floor of the master bedroom ensuite.

















Also the floor of the wet area of the ensuite was laid.





















On the other side of the extension the
carpentry for the floor of the loft was started.













A view from underneath of the loft floor from what will be the kitchen area.























The main bathroom window was installed.



















Plus some repair work on the northern wall of the old part of the house was undertaken.

Tuesday, January 25, 2011

Carpentry has started







Carpentry has started at the site. Today the carpentry for the floor of the walk-in-robe and ensuite for the master bedroom.















A view towards the master bedroom.

Monday, January 24, 2011

More bricks in the house






Today the doorway for the main
bathroom was done in bricks. Also the doorway into the master bedroom was bricked up.


























This is a view of the bricked up doorway in the master bedroom as viewed from the extension.





















The nib wall in the lounge area of the extension was constructed as well.












Thursday, January 20, 2011

Another brick in the wall







The new wall in the
master bedroom was constructed today. Looking at it from inside the old part of the house.



















Looking at it from the extension.

Wednesday, January 19, 2011

Another day of bricks








The brick layers finished the entrance into the laundry from the pantry.




















Also the stairs up into the old part of the house from the extension were started.






Tuesday, January 18, 2011

Brick layers are back again









The brick
layers are back to complete the brick work. Today they worked on the laundry area.
The alcove in the forefront of the picture is for the fridge.















This newly built wall in the spare bedroom (old lounge room) forms part of the loft. On the other side will be the floor of the loft/ceiling of the laundry about two thirds up the wall.



















This photo gives a sense of the main corridor in the house.

Monday, January 17, 2011

Main Bathroom





The floor of the main bathroom was removed today. The mortar between the bricks of the inner wall under the window cut out (northern wall) is crumbling so that wall will need to be rebuilt.

Saturday, January 15, 2011

Recessing of sliding doors








We decided to recess the sliding door frames into the concrete to make them more flush with the concrete floor.



















This meant cutting into the concrete. An extra two days of work but it will be worth it.

Wednesday, January 12, 2011

Manhole & Main Bathroom






The new year has began and the builder is back on the job. Work has started on creating a manhole (in the southern wall) to get under the floor in the old part of the house.


















The old main bathroom has also been demolished. The brick layers should be back next week to complete the internal walls of the extension. This should allow the framing to start for the roof.